TPLS Interiors Ltd delivers the interior package on commercial refurbishments across London: suspended ceilings, dry lining, partitions and tape and jointing. Refurbishment is a different job from new build, because the building has already made decisions for you. Director-led, London-based, trading since 2006.

TL;DR

A commercial refurbishment succeeds or slips on three things: knowing what is really behind the existing finishes before you price, sequencing strip-out and new work so trades are not waiting on each other, and phasing around occupation where the building stays live. Ceilings, partitions and dry lining interact at every head and abutment, so running them as one package removes most of the interface problems that cause refurbishment overruns. Call 0204 572 0878.

Key Takeaways

  • Survey the existing building before pricing, because drawings for older stock are rarely accurate
  • Strip-out reveals the problems, so build a contingency decision point into the programme after it
  • Cat A and Cat B scopes overlap at the ceiling and partitions, so agree who owns what early
  • Occupied buildings need phasing, dust control and out-of-hours work planned in the RAMS
  • One contractor for ceilings, partitions and dry lining removes the head and abutment arguments.

New build gives you a clean shell and accurate drawings. Refurbishment gives you a building that has been altered several times by people who did not leave notes. The interior package is where that shows first, because ceilings and partitions are what get opened up.


Survey Before You Price

The single biggest cause of refurbishment overruns in our experience is pricing from drawings that no longer describe the building. On older London stock it is normal to find a ceiling void that is shallower than shown, services rerouted, partitions added without records, and soffits that are not level.

Before we price the interior package on a refurbishment, we want to know:

  • Void depth and what is in it, measured, not assumed
  • Existing ceiling system, grid profile and whether any of it is being retained
  • Soffit level and condition, because new hangers need sound fixings
  • Which existing partitions are staying, and how they meet the new ceiling
  • Whether any ceilings or partitions form part of the fire strategy

A morning on site with a few tiles lifted answers most of that, and it is far cheaper than a variation in week four.

Commercial refurbishment interior works by TPLS Interiors Ltd in London

Ceiling and partition works on a London commercial refurbishment

Suspended ceiling installation during commercial refurbishment by TPLS Interiors Ltd

New ceiling tile installation in a refurbished office


Strip-Out and the Decision Point After It

Strip-out is where refurbishments reveal themselves. Once the old ceilings and linings are down, you see the real soffit, the real services and the real condition of the walls.

The sensible approach is to build a short review into the programme straight after strip-out, before new work starts. That is when to confirm hanger fixing points, check walls for lining, and resolve anything the survey could not see. Programmes that run strip-out straight into new installation with no pause tend to absorb the surprises as delay later rather than as a decision early.


Cat A, Cat B and the Overlap

On commercial office refurbishment, Cat A usually means the landlord’s base fit-out, typically including a finished ceiling, while Cat B is the occupier’s fit-out, which often includes meeting rooms, partitions and changes to lighting and services.

The overlap causes problems. A Cat A ceiling installed across an open floor is then opened up for Cat B partitions, and the partition heads, ceiling cuts and void barriers all need detailing. If the Cat B partitions need acoustic separation, a ceiling installed without allowing for it may need partly removing.

Where the occupier is known, it is usually cheaper to coordinate the two scopes before the Cat A ceiling goes in. Where they are not, we advise on detailing the Cat A ceiling so Cat B partitions can go in cleanly later.


Working in Occupied Buildings

A lot of London refurbishment happens with the building partly or fully in use. That changes the method more than the materials.

Ceiling grids and metal stud partitions are dry builds, which helps. Tape and jointing and decoration are the dusty, time-consuming parts, so they get the most planning. We agree phasing, dust screens, out-of-hours working, noisy-work windows and access routes in the RAMS before mobilisation, and we stick to them.

Running ceilings, dry lining and tape and jointing as one package matters even more in occupied space, because every extra trade handover is another night of disruption.

Where a refurbishment package has stalled with another contractor, we can survey what has been done, agree what needs correcting and pick it up. That is a large part of our work.


Refurbishment coming up?

Send us the drawings and let us survey before you price. It is the cheapest risk reduction on the job.

Call 0204 572 0878Submit Tender Documents


Working with TPLS Interiors

TPLS Interiors has been delivering suspended ceilings, dry lining and partitions across London since 2006. Founded by Tomasz Platek and Lukasz Swider, whose initials give the company its name, it remains director-led on every project.

We work as a subcontractor to main contractors and directly with project managers, architects and commercial occupiers, and we also step in on stalled packages where a programme needs recovering.

We work on commercial and larger residential projects. We do not take on small works or single room jobs.


Frequently Asked Questions

Q: What is included in a commercial refurbishment interior package?

Typically suspended ceilings, dry lining and wall linings, metal stud partitions, tape and jointing, and associated details such as access panels, bulkheads and void barriers. We deliver these as one package so the interfaces are handled by one contractor.

Q: Why survey before pricing a refurbishment?

Because drawings for older buildings are often inaccurate. Void depths, services, soffit levels and existing partitions regularly differ from the records, and finding that during installation becomes a variation and a delay.

Q: What is the difference between Cat A and Cat B fit-out?

Cat A is usually the landlord base fit-out, often including a finished ceiling and basic services. Cat B is the occupier fit-out, such as meeting rooms, partitions and changes to lighting and services. The two overlap at the ceiling and partitions and need coordinating.

Q: Can refurbishment work be done while the building is occupied?

Yes, with planning. Ceiling grids and stud partitions are dry builds. Dustier stages such as tape and jointing are phased, screened and often scheduled out of hours, all agreed in the RAMS before work starts.

Q: Can you take over a refurbishment package from another contractor?

Yes. We survey what has been done, identify what needs correcting, agree a programme and pick the package up. It is a regular part of our work.

Q: Do you work on residential refurbishment?

On larger residential projects, yes. We do not take on small works or single room jobs.


Need an interior package priced?

Get a quote for your London refurbishment.

Get a Quote

Or call 0204 572 0878

LS

Lukasz Swider

Lukasz co-founded TPLS Interiors in 2006 alongside Tomasz Platek. He oversees every project personally and has delivered ceilings, dry lining and partitions across more than 500 commercial sites in London for main contractors, developers and corporate occupiers.

✓ Fully insured
✓ RAMS provided
✓ CSCS-qualified teams
✓ Director-led

Disclaimer: The information on this page is general guidance only. Product specifications, standards and manufacturer documentation are revised over time. Project costs, timelines and system specifications vary depending on site conditions, building regulations and scope of works. Always confirm requirements with the design team and verify product data against the manufacturer’s current documentation before specifying or ordering.